Construction Works Update, March 2025 

Blog

Posted 2 years ago

Dear Resident, 

We continue to make great progress on-site at Bermondsey. We are working hard to minimise disruption to our neighbours and appreciate your patience as we continue work to deliver the new homes, shops, and public spaces for Bermondsey.  

We are also delighted to announce we will be supporting Cherry Gardens TRA in their creation of a musical play and their ongoing heritage work into Bermondsey’s rich history. 

CONSTRUCTION QUERIES 

Ana is our dedicated community liaison officer who some of you will have met at residents’ meetings. Should you have any construction related questions, concerns or issues you’d like to discuss please talk to her at the resident meeting or reach out using the contact details below:  

Email: ana.santos@munnellys.com     Telephone: 07907 725 882

You are also invited to join us in person for our next residents’ construction update meeting at 9:30am on Thursday 27th March 2025. Please contact us using the details above to confirm attendance. 

We continue to actively monitor construction vehicle movements to ensure the safety of all road users, including all measures we previously put in place to minimise the transfer of dust and mud to the surrounding roads. Daily noise and vibration readings continue to be taken and monitored to ensure environmental control limits are adhered to. 

CONSTRUCTION WORKING HOURS 

We are committed to being a considerate neighbour and will be working hard to ensure that any disruption caused by our construction work is kept to a minimum. Our usual construction working hours are as follows: 

8am to 6pm, Weekdays 

9am to 2pm, Saturdays 

We will continue to endeavour to provide advanced notice of any upcoming out of hours works if required in the future.  

UPCOMING WORKS 

The slipform will be removed from tall 21 storey RC Concrete core over this coming weekend with EHO approval to avoid unnecessary H&S risks. 

In order to continue progress on site and install vital infrastructure to service the future homes, there are some upcoming activities that may impact local traffic. 

  • Drummond Road District Heat Network Connections; These were carefully planned to ensure there was no down time impacting educational teaching at the school due to no heat, this was achieved. There was a slight unknown encountered in the ground which will extend the civils works by a few days (extent tbc) 
  • Webster Road, crossing Clements Road from our site will have UK Power Networks commence installation of HV ducts to bring power to Buildings 1-4 &5 from 01 – 02/03/25, this is at short notice after an opportunity arose to start earlier and does not require a road closure. 
  • We plan to commence a phased road closure from 03/03/25 on Clements Road working West to East until 06/05/25.  

We will have continued coordinating with Thames Water to ensure collaborative working to minimise local highways disruption.  

We have now completed UK Power Solutions bringing power to our site from Verney Road and now only have works local to our site to complete. 

EMPLOYMENT WEBSITE 

There are currently a range of opportunities across the scheme from full time jobs to short courses, please visit the below site or scan the QR code for more information. 

https://opportunitybermondsey.recsite.com/ 

STAY UP TO DATE 

Our team will continue to share updates as the project continues. Please visit the Bermondsey Project website for more information www.greystar-bermondseyproject.com/. Thank you for your understanding as we continue work to deliver this important development.  

Kind regards, 

The Bermondsey Project Team 

 

Upcoming construction work 

Construction works are continuing on the both the old school site with superstructure works across all buildings progressing at pace. The old school site brickwork facade and windows are now visible to the surrounding area. The first homes remain on target to be ready in September 2025 with the District Heat Network connection milestone having just been achieved.   
Strengthening works on the retained structure and foundations of the Old Packing Factory (Building F) are almost complete on the ground floor.    
Superstructure works are progressing well on all building on the Biscuit Factory Site and 1-4 & 5 on the old school site. The concrete cores on ST continue to progress ahead of the frame and DE core is now complete at Level 21. The next milestone in the period on Building F will be the commencement on the new steel transfer deck form 03/03/25.   
Pavement works around the Charter School are being coordinated with the school and Southwark Council to complete in the most suitable holiday period.   
London Square have been appointed as the delivery partner for the social housing on-site,  enabling works and site set up have progressed in the period as London Square progress through the building regulatory requirement process. 